9, pre-trial preparation
* Use the unit asked me to plant commissioning personnel to the scene, it must
make the following points to:
1, the main components in place, as required adjustment, testing, meet the
accuracy requirements, parts complete, intact.
2, power supply and motors wiring is correct, the motor in normal operation,
hydraulic station should add a little hydraulic oil (initial fill is good).
3, installed feeding tube, trachea, plumbing and other piping and all valves
and shall be free from obstruction to avoid rework.
4, pipe valves used in the road, such as pneumatic valves, should take a good
gas supply pipe, and light wires, pneumatic valve should be action, such as
sensitive.
5, auxiliary equipment (such as pumps, air compressors, etc.) are installed
with complete integrity.
6, should be ready enough slurry, gas supply, water and other conditions to
meet the test requirements.
7, according to slurry filtration requirements, flocculation of materials that
need to be a suitable coagulant supply thereafter.
8 pairs of slurry required to test, test users should be equipped with professional
laboratory personnel as well as all the necessary laboratory equipment and
reagents used.
9, with a good maintenance man 1 ~ 2, operators several others.
10, with general tools, such as adjustable wrench, hammer, plier, screwdriver,
pipe pliers, hex wrench etc., and have a small amount of oil, lubricants, cotton
yarn and other auxiliary materials for use.
11, after the completion of the preparatory work, please send a request to
debug notification faxed to my company, the company will send professionals
to debug. |